Omniplan scheduling effort and duration8/15/2023 ![]() ![]() In a June 2007 evaluation of OmniPlan 1.0, Macworld, a web site and monthly computer magazine dedicated to Apple Macintosh products, found the customizability of OmniPlan 1.0 to be "superior", but said the software was unlikely to meet the needs of project managers with multiple, complex projects. The software was released as a public beta on June 6, 2006. OmniPlan is a planning and project management software product from The Omni Group, headquartered in Seattle, Washington. ![]() A 40 hour task assigned to a resource who works 8 hours per day but has next Friday off will extend an extra day in the schedule to account for that missing day. ![]() Even though it doesn't take your M8h Tu6h W0h Th10h F4h Sa2h Su14h schedule into account when displaying durations in the schedule (a 16 hour task might be displayed as quite a few different things in that work week depending on when it started), it does do so when assigning the work. It gets a bit more confusing when you have weeks and days that aren't all the same length, but if you've got a better solution, I'm sure the Omni crew would be interested in hearing about it. The ability to have non-standard work weeks is what makes this feature necessary. As a rule of thumb, you probably want the smallest unit you would ever assign to a task checked, maybe the next smallest as well. If you only have hours clicked, everything OP displays will be expressed in hours or decimal fractions thereof. There is no correlation with the number of hours you might diagram in your custom work week, so you do want to be careful.Ĭlick the boxes in the Durations display for the units you want to see. If you put 5 hours/day in the ECF table, then enter 2d for the effort on a task, 10 hours will be stored as the effort. The ECF are also used to convert from bigger units to smaller. 8 hours/day, 20 hours/week, 30 hours/month, 100 hours/year won't get you an error message, but probably will get you misleading results! If you tab from one box to the next, the values will be forced to correspond properly. ![]() It is possible to set inconsistent values for the Effort Conversion Factors, so watch out. If you have a work week with differing numbers of hours per day, but a constant number per week, I'd suggest using the average hours per day. Furthermore, longer tasks will be shown as bigger units, so 400 hours of work will show up as something like 10 weeks (assuming the default 8 hours per work day). So for example, a task requiring 8 hours of effort will show up as 8 hours instead of 28,800 seconds. They are used to convert the internal representation of effort and duration into something a bit more user-friendly. I admit I'm a newbie at OmniPlan, but I am totally stumped by this menu-what it does, what it can do for me, why I have to set it up, how setting it up might screw up display data.Īny help anyone can provide would be greatly appreciated. How, then, are the figures on the right-the "Effort Conversion Factors" going to affect how durations and effort are displayed? And where? I have non-standard work week days-some are longer than others-and this menu doesn't seem to allow that granularity. So I guess I have to check some of the boxes on the left. If I uncheck all the boxes on the left, my Effort and Duration columns in the task view go blank and I don't get to see that data anymore. I know that the "Effort Conversion Factors don't actually change the working hours for the project, just the way durations are displayed"-according to the manual, but it seems I'm obliged to do something here. The left side is "Durations Display" and the right side is "Effort Conversion Factors." This is under Inspector, Project, Formatting. What are Effort Conversion Factors and why do I need them? This is inducing quite a lot of head scratching, and my scalp is suffering! ![]()
0 Comments
Leave a Reply.AuthorWrite something about yourself. No need to be fancy, just an overview. ArchivesCategories |